Good morning, ladies and gentlemen. Thank you for standing by. Welcome to the AltaGas Fourth Quarter 2024 Financial Results Conference Call. My name is Sylvie, and I will be your operator for today's call. [Operator Instructions] As a reminder, this conference call is being broadcast live on the Internet and recorded.

I would now like to turn the conference over to Aaron Swanson, Vice President, Investor Relations. Please go ahead, Mr. Swanson.

A
Aaron Swanson
executive

Good morning, and thank you for joining AltaGas' Fourth Quarter 2024 Results Conference Call. Speaking this morning will be Vern Yu, President and Chief Executive Officer; and James Harbilas, Executive Vice President and Chief Financial Officer. We're also joined here today by Randy Toone, President of our Midstream business; Blue Jenkins, President of our Utilities business, and Jon Morrison, Senior Vice President of Corporate Development and Investor Relations.

This call is being webcast, and we encourage following along with the supporting slides that can be found on our website. We will refer to forward-looking information on today's call. This information is subject to certain risks and uncertainties as outlined in the forward-looking information disclosure on Slide 2 in the presentation. Prepared remarks will be followed by a question-and-answer session.

I will now turn the call over to Vern.

D
Dai-Chung Yu
executive

Thanks, Aaron, and good morning. It's great to be here today to discuss our strong performance for Q4 and 2024 as a whole. I'll share key highlights from the year, provide an update on our 2 major midstream growth projects, talk about some recent commercial successes and close by discussing some of the macroeconomic trends that are creating bigger tailwinds for AltaGas' growth.

Then I'll turn it over to James, who will provide detailed review of our Q4 financial performance and review our strategic priorities. I want to start by thanking our employees and contractors for our strong results and doing it safely. Safety performance improved by 33% in 2024 over 2023, which gave us our best safety year ever, delivering strong results and doing it safely is paramount. So thank you.

Let's turn to Slide 4. We delivered 2024 normalized EBITDA of $1.77 billion, which was up 12% year-over-year. And this was at the top end of our 2024 guidance range. Our 2024 normalized EPS of $2.18 was up 15% year-over-year and was in the upper half of our guidance range. We continue to execute and advance key growth projects across our business. Within midstream, we delivered record global export volumes of more than 122,000 barrels per day of LPG to Asia in the year with the VLGC leaving our terminals every 4 to 5 days. Customer demand to access our terminals was strong.

The actions around U.S. tariffs on Canadian Energy is creating uncertainty and driving higher demand for West Coast access. This further highlights the long-term advantage of AltaGas' global export platform. With U.S. tariffs, it's even more critical to connect Canada's energy exports to Asian markets, reinforcing the need for our third West Coast export facility, REEF, which commenced construction last August. We also made material progress on Pipestone II in 2024, which will add much needed gas processing and liquids handling capacity to the Alberta Montney.

Our midstream business saw important commercial successes in 2024. With the signing of 3 long-term integrated gas processing and liquids handling contracts at Townsend and Pipestone I. And we doubled our global export tolling in 2024 over 2023. Turning to our utilities business. We made large investments in 2024, deploying more than $730 million of capital. This allowed us to make our system safer and more reliable while expanding our network by adding more than 12,000 new customers.

On the regulatory front, we filed a new rate case in D.C. in Q3. We also extended our current ARP modernization program in D.C. to the end of 2025. As we continue to work with the D.C. Commission to put a new 3-year modernization program in place. Corporately, we continue to reduce our leverage which provides additional financial flexibility to execute on our strategic plan.

Let's turn to our major midstream growth projects where we've made strong progress on construction. Both Pipestone II and REEF remain on time and on budget. Let's start with REEF on Slide 5. Multiple work streams are currently underway, including upland's work, rail and utilities construction, off-site fabrication and jetty construction. One of the key risks of the project, the earthwork site preparation is mostly behind us. We are 90% complete on overburden removal and on track to finish by the end of this month. We were able to store all of the overburden on the island, and this is a positive cost savings. Rock blasting is progressing well and on track to be complete in the next few months.

Work has begun on site grading and the facility foundations. Off-site fabrication in Asia is progressing nicely with the accumulator and bullets approximately 65% complete. Compression and refrigeration fabrication is also progressing with that work being done off-site in Western Canada. All of this fabrication work is taking place in controlled manufacturing environment on a modular basis. It will then be assembled on site, which materially reduces project execution risk.

Work on the jetty is progressing. We now have 78 piles driven into the seabed. We have seen better efficiency over the past 6 weeks as bad weather slowed progress in December and January. As we announced in February, we have now met our REEF export tolling target, which significantly derisks our global export business. We now have the option of adding further tolling contracts at our discretion.

Turning to Pipestone II on Slide 6. The project is also progressing well. The acid gas injection wells and the gas gathering system are complete. Principally, all project work has either been executed or is under fixed price EPC awards. As you can see in the pictures on the right-hand side of the slide, there has been strong progress on facility assembly over the past 8 months with roughly 65% of the facility now complete.

Like REEF, a significant portion of the remaining work is taking place in controlled manufacturing environment and then will be assembled on-site following our standard project execution model. There have been no safety or quality issues experienced on-site and the project remains on track for December 2025 in-service date. As a reminder, the facility is 100% backstopped by long-term take-or-pay contracts with marquee producers.

Turning to Slide 7. I want to discuss our recent agreement with Keyera. We view this as a positive development for both companies. The agreement leverages our respective infrastructure to drive the best industry outcomes. For AltaGas, we secured 12,500 barrels per day of export tolling volumes under a 15-year agreement, which provides our company with stable and predictable export volumes and cash flows.

We also gained access to Keyera's extensive rail, storage and logistics network in Alberta's industrial heartland, which will allow us to efficiently connect LPG volumes to our global exports network. Through this transaction, we also secured long-term capacity at KFS, with take-in-kind rights. LPG from our Pipestone plants will now be fractionated at KFS and then move to global markets through our export facilities. Our agreements allow Keyera to provide its customers increased access to Asian markets and our committed volumes help backstop debottlenecking and expansion at KFS.

Slide 8 highlights our long-term tolling contracts. We expect our tolled export volumes, which have more than doubled since 2023 to remain around today's level for the next couple of years, before arising to more than 100,000 barrels per day after REEF comes online. We believe this level of tolling strikes the appropriate balance of having stable and predictable cash flows, while continuing to benefit from the structural merchant spread between Canada and Asia. This results in AltaGas' long-term EBITDA coming from take-or-pay, cost-of-service or fee-for-service contracts to reach approximately 90%.

Turning to Slide 9. The short and long-term demand for energy continues to rise. Natural gas is and will continue to be the most reliable, affordable and scalable solution to meet this growing energy demand in North America and globally. Natural gas continues to represent 2/3 of household energy consumed in the United States and has a 300% to 400% cost advantage over electricity for space heating. As such, the long-term demand outlook for natural gas and our utilities is robust.

When we layer in the expected increase in gas demand from coal retirements and the addition of data centers, the market is pointing to up to 25% plus increase in gas-fired power demand by 2030. The Canadian midstream outlook was equally strong as shown on Slide 9. AltaGas continues to benefit from 2 strong macro tailwinds. The first, growing natural gas production volumes from Western Canada due to increased egress from LNG Canada. And the second is the rising demand in Asia, where LPG consumption is expected to increase by more than 40% by 2040, which will need to be satisfied with imports from North America and the Middle East.

Canadian natural gas production is expected to rise 25% by 2030, which will primarily come from the Montney. This increase will deliver higher NGL volumes that are already oversupplied in Western Canada. And all of these new NGLs will need to be exported to global markets. These tailwinds in the energy fundamentals will provide additional long-term growth opportunities for AltaGas, which James will discuss along with providing further details on our fourth quarter performance, our forward outlook and our strategic priorities.

D
D. James Harbilas
executive

Thanks, Vern. Within our utilities, which are shown on Slide 11, we continue to have strong long-term growth opportunities. We have more than $1.7 billion of ARP modernization capital to be deployed over the next 4 years. These programs allow us to balance the need of improving the long-term system safety and reliability of our network while ensuring we could deliver timely returns on our capital to our shareholders.

We continue to see strong new customer demand that has averaged approximately 1% new meter growth per year which is approximately 40% above the national average over the last 10 years. We're also working with our regulators in Michigan to advance the Keweenaw Connector Pipeline and expect to seek regulatory approval in 2025. The project will be similar in size to the Marquette Connector and will improve system reliability and extend service to 14,000 customers in the Keweenaw Peninsula.

And finally, the data center opportunity for AltaGas continues to be very encouraging and complements our already robust utilities growth outlook. As you can see on Slide 12, PJM is expected to realize capacity shortfalls as early as 2026. This is creating the need for data centers to look at alternative energy solutions. We continue to work with numerous data center developers in Northern Virginia to build pipeline interconnects to provide natural gas for on-site power generation.

Business development and engineering work on these opportunities is expected to progress through 2025 with potential construction in 2026 and onwards. We are pursuing these opportunities on a derisked basis through traditional rate-regulated investments with unique rate structures. Within midstream, while we are acutely focused on delivering REEF and Pipestone II, we are also continuing to evaluate other organic growth projects in our development pipeline as a result of strong customer demand, which we highlight on Slide 13.

At Dimsdale, which is a Montney natural gas storage facility that we acquired as part of the Pipestone acquisition, we are evaluating a potential 2-stage facility expansion based on strong customer interest for additional storage in the area. Current storage capacity of the asset is 15 Bcf, but we can increase capacity to 69 Bcf, and the facility can be utilized for LNG balancing needs in the Montney. We are currently evaluating a RIPET methanol removal project in the near term, which will increase the number of downstream markets that RIPET can ship LPGs to in Asia and brings price optimization opportunities.

We continue to advance work at North Pine, which is our frac in Northeastern BC. Although we recently completed an optimization project to increase throughput, volumes at the facility are approaching its nameplate capacity. We are currently working through engineering and commercial to evaluate a substantial increase of capacity to meet our customer needs in the area. We also continue to advance Pipestone III to fulfill the additional needs for deep cut gas processing capacity in the Alberta Montney.

We continue to see strong demand in the area for gas processing infrastructure. And lastly, we are advancing regulatory and engineering work for additional phases of REEF given the commercial success we have had on the first phase and the importance of ensuring more Canadian energy reaches global markets at premium prices. We believe having a wide range of projects with different gestation periods will allow us to continue to grow the enterprise on a consistent basis while having optionality to advance the best projects.

As always, we are focused on moving these opportunities forward in a methodical manner as part of our long-term strategic plan and balancing our corporate priorities of growing the enterprise, deleverage the balance sheet and returning more capital to our shareholders over time.

Turning to our financial results in more detail. We are pleased with our fourth quarter and full year 2024 results.

Fourth quarter normalized EBITDA of $520 million was up 4% year-over-year, while full year normalized EBITDA of $1.77 billion was up 12% year-over-year and was at the top end of our 2024 guidance range. Fourth quarter normalized EPS of $0.76 was in line with the fourth quarter last year. While 2024 normalized EPS of $2.18 was up 15% year-over-year and was in the upper half of our guidance range.

Operational execution was strong across the enterprise in the fourth quarter and was reflective of the purposeful steps we have taken to execute on our strategic priorities, including commercial derisking, deleveraging and cost management initiatives. In terms of segmented results, let's start with Utilities on Slide 15.

Utilities normalized EBITDA was $336 million in the fourth quarter of 2024, compared to $311 million in the same quarter of 2023. The largest drivers of the 8% year-over-year growth were cost management, increased contribution from investments in rate base over the past year and higher revenue from the 2023 D.C. rate case decision. These factors were partially offset by warm weather in D.C. and Michigan, which do not have weather normalization, and lower contributions from the retail business, which had stronger performance in the fourth quarter last year.

Utilities O&M costs were down 7% year-over-year in the fourth quarter as we continue to focus on process efficiencies, centralizing functions and core operations. As we have shared in the past, we will continue to operate with a high degree of capital costs and regulatory discipline in the years ahead. We deployed $178 million of capital in our utilities during the fourth quarter and $722 million for the full year. This included $85 million of modernization investments in the fourth quarter and $359 million for the full year.

These investments are focused on upgrading the network to improve safety and reliability. Over the past 5 years, these investments have helped contribute to a nearly 50% reduction in leak rates across the WGL network, which demonstrates the importance of these ongoing investments. Asset modernization and system betterment will remain a key focus in 2025 and beyond, which will allow AltaGas to deliver the lowest cost and most reliable form of residential and commercial heating in our jurisdictions.

Turning to the midstream segment on Slide 16. Normalized EBITDA of $182 million for the fourth quarter was consistent with last year, while full year midstream EBITDA of $785 million was up 15% year-over-year. Specific to the fourth quarter, stronger global export volumes and higher throughput across the midstream value chain were offset by lower extraction volumes due to ethane reinjection, a material increase in tolled export volumes which delivered increased predictability but carry lower margins and lower contributions from MVP due to the recording of equity earnings relative to AFUDC recorded in 2023 when the pipeline was still being constructed.

The first 2 quarters of operations at MVP showed strong operating performance with no surprises and has run near capacity to start 2025. The global exports business shipped more than 122,000 barrels per day of LPGs to Asia in the fourth quarter, which was up 34% year-over-year. This included approximately 82,000 barrels per day across 13 ships at RIPET and 40,000 barrels per day across 7 ships at Ferndale.

As we highlighted coming into 2024, one of our major strategic initiatives was commercial derisking, which we delivered on with tolling volumes on exports approximately double 2023 levels. Despite Canadian natural gas price weakness throughout the fourth quarter, AltaGas' facility volumes were strong with approximately 15% year-over-year growth across our midstream value chain. This speaks to the strategic location of our assets in some of the most prolific resource plays and our commercial relationships with high-quality customers.

This included our G&P volumes increasing 12% year-over-year in the fourth quarter with Townsend showing the strongest growth, with volumes up over 20% year-over-year. While our fractionation, extraction and liquid handling volumes were up 32% year-over-year in the fourth quarter, led by North Pine and Harmattan. Currently, we have 87% of AltaGas' expected first half 2025 global export volumes, either tolled or financially hedged with an average FEI to North American spread of approximately USD 19 per barrel for the non-tolled volumes.

Given the uncertainty surrounding U.S. tariffs on Canadian LPGs being exported into the U.S., the 2025, 2026 NGL recontracting season is much more fluid than normal with multiple moving pieces. As such, we are taking a measured approach on our market positioning. We will have a more comprehensive update on our procurement and financial hedging activities when we report first quarter results.

We continue to be active locking in costs across the export value chain with substantially all of AltaGas' 2025 Baltic freight exposure effectively hedged through a combination of time charters, financial hedges and tolling arrangements. In the Corporate and Other segment, we reported normalized EBITDA of $2 million compared to $9 million in the fourth quarter of 2023.

These results were mainly driven by lower year-over-year contribution from Blythe due to CAISO transmission outages temporarily reducing Blythe's generating capacity and merchant opportunities.

Turning to our outlook on Slide 17. We outlined the 2025 guidance headwinds and tailwinds that we see so far. Overall, the opportunities and risks are fairly balanced, and we are reiterating our 2025 guidance ranges of normalized EPS, $2.10 to $2.30 and normalized EBITDA of $1.775 billion to $1.875 billion. Moving to the 2025 capital budget on Slide 18. There have been no major shifts in our capital plan, and we expect to deploy $1.4 billion of CapEx in 2025, including ARP programs at the utilities and the REEF and Pipestone II projects in midstream. As shown on Slide 19, we reduced our adjusted net debt by approximately $460 million year-over-year in 2024 and exited the year with 4x adjusted net debt to normalized EBITDA, excluding hybrids, and continue to move towards our 4x target metric.

We have demonstrated considerable progress on this objective over the last several years, reducing leverage by more than half since 2018. While the journey continues, we expect the potential monetization of MVP to accelerate our path to achieving our targets. We are currently in the price discovery phase for our 10% nonoperated stake in the pipeline and expect to provide an update during the first half of 2025.

In closing, we are very happy with the fourth quarter and 2024 results. We made considerable progress across all corporate priorities while creating strong shareholder value. As we look ahead on Slide 20, we will continue to focus on many of the strategic priorities we had in 2024, which continue to surface shareholder value. Specifically, we are focused on growth, commercial derisking and strengthening the enterprise with a focus on long-term compounding per share value, as evidenced by our track record on Slide 21 over the past 5 years.

And with that, I will turn it back to Vern for a quick closing comment.

D
Dai-Chung Yu
executive

Just before we turn to Q&A, I want to take a moment to discuss the potential impact of U.S. tariffs and how the new administration could impact our business. We all know that Trump Administration's energy policies are highly supportive of natural gas in our utilities. The administration has already started to unwind space heating electrification policies, which will enhance energy affordability, reliability and security for our utility customers.

The administration is highly supportive of energy infrastructure investments. [ FIMSA ] has already started highlighting the importance of upgrading aging natural gas infrastructure, and we expect [ FIMSA ] to become more active in its support of ARP programs at gas LDCs. In terms of U.S. tariffs on Canadian energy, the situation is obviously dynamic, and the impacts will be ultimately determined by the size and duration of tariffs. With respect to our 2025 capital program, we are well protected and do not expect an impact on our current capital cost estimates or any supply chain challenges.

In midstream, tariffs will have a negative impact on the cash flows of our upstream customers, but tariffs will be partially offset by a stronger U.S. dollar. And as a result, we do not expect material changes to natural gas and NGL production volumes. Canadian NGL prices will partially discount to offset the cost of tariffs, while Asian prices will remain unchanged. This will cause a wider Canada to Asia LPG spread, which we expect to be modestly additive to our merchant export margins.

In terms of our utilities, we expect only a modest impact on our operations and customer bills. SEMCO will potentially face some higher gas costs, which it will flow through to its customers as approximately 15% of SEMCO's gas supply comes from Canada. Should tariffs remain in place in the long term, this will drive higher inflation at our utilities and lead to higher customer bills. And with that, we'll open the call up for Q&A.

Operator

[Operator Instructions] And your first question will be from Rob Hope at Scotiabank.

R
Robert Hope
analyst

First comment -- or first question is on the 2025, 2026 NGL year. Just realizing that it is dynamic, can you maybe add a little bit more color on why you're not giving the full year guidance and potentially holding some back? Is that to reflect the potential that you could see increased margins if tariffs do get enacted or when they get enacted? And I guess, secondly on that, are you seeing new customers or increased appetite for tolling from the facility due to diversification of markets?

D
Dai-Chung Yu
executive

Rob, it's Vern here. Can you just clarify that first part of your question on the -- what you mean by the NGL year and the guidance?

R
Robert Hope
analyst

Yes. Like I'm just wondering for the export volumes that you're financially hedging, you're only giving the 87% for H1, and you didn't notice that it is dynamic, the environment. Just wondering if you're holding -- if you're willing to take some additional exposure there just given the fact that the spreads could widen in your favor?

D
D. James Harbilas
executive

Rob, it's James here. No. So like when we -- obviously, the recontracting year runs from April 1 to March 30 of the following year. And we're about 3 weeks away from crystallizing our supply and what split is going to be merchant versus tolling. Obviously, with our effort to derisk our cash flows, we expect a slightly higher tolling percentage.

So once that comes into view, then we can actually go ahead and hedge out the remaining merchant barrels, and that's when we'll be providing guidance for the back half of the year. So that's really why the hedging book and the disclosures are focused on the first half of the year. We need the tolling versus merchant split to crystallize in the next 3 weeks, and then we'll start to layer on financial hedges on our remaining merchant barrels for the balance of the year.

D
Dai-Chung Yu
executive

The only thing I'd add to that is obviously, with the uncertainty of tariffs, the demand for tolling is extremely high. So we just need to work through with our customers, which tolling contracts we're going to accept for this year.

R
Robert Hope
analyst

I appreciate that. And then in the prepared remarks, you highlight a number of kind of the next phase of growth for the company, whether it be kind of Dimsdale or Pipestone III. How do you think about the pacing of these growth projects just given the good spend for REEF right now as well as the desire to move down leverage?

D
Dai-Chung Yu
executive

Well, I'll start off and then James and Randy can chime in here. As you know, we're almost done Pipestone II. So that's a big significant use of capital in 2025. And we will be -- have made very significant progress in REEF construction this year as well. So as we roll forward in time with some of these projects, the bigger -- most of these projects take a year or 2 to build out. So we'll have more capacity once REEF is finished to look at where is the best place for us to deploy our capital. Obviously, we have lots of opportunity in the utility as well, where we can grow rate base by up to 8% per year for the foreseeable future. So it's an envious position to be in to be able to have to allocate capital to the best returning projects on a risk-adjusted basis.

D
D. James Harbilas
executive

Yes. And Rob, the only thing I'll add, and we touched on it in our prepared remarks. If you look at the portfolio of projects that we have in front of us from an organic growth standpoint, they all have different gestation periods, and a lot of that is driven by the length of customer discussions to be able to get some commitments to be able to move forward to an FID and obviously, different permitting time lines with respect to these projects as well. So that will help us to be able to fund some of these under our existing investment capacity because we could stage them just given some of those dynamics that would come into play.

Operator

Next question will be from Maurice Choy at RBC Capital Markets.

M
Maurice Choy
analyst

I just want to start off with REEF. I think in your prepared remarks, you mentioned that productivity is increasing on in-water piling. There's been positive cost savings on overburden removal. Will all these positive updates planned? Or are we trending below budget? And a quick add-on to that, seeing as you're going through your engineering work for the future phases, can you speak to what work you've done or can do to somewhat prebuild some of the infrastructure for some of these future phases?

D
Dai-Chung Yu
executive

Sure. So Maurice, as you know, the first phase of REEF does prebuild a whole bunch of infrastructure for the subsequent phases of REEF. The biggest things we're obviously doing is the rail facility and the jetty. The rail facility will be able to accommodate when it's complete 3,000 cars. So it's a very sizable rail loop. Future phases would still require incremental rail offloading, but the rail loop is prebuilt for multiple phases of expansion. That's similar for the jetty as well. The jetty will be able to accommodate significantly more NGL loading than we're doing in Phase 1.

So subsequent phases of REEF will be materially lower on a capital cost basis per barrel of export. So that's very -- it's a good tailwind for us. As far as commenting on the REEF capital estimate, it's unchanged at this point. I think we talked about in our remarks that we have about 50% of the project either incurred or under fixed price EPC contracts with that rising to about 60% in the next month or 2. But there's still a few pieces of work where there is a little bit of risk.

So I don't think it's appropriate to change our capital cost estimate at this point. But a couple of the big pieces of risk have been materially derisked. The biggest, as I think I talked about in the prepared remarks, was the earthworks phase, given that this is a greenfield site, the geotechnical work of removing the muskeg and the rock blasting were probably the biggest risk we had to a change in capital cost.

M
Maurice Choy
analyst

Understood. That's great color. Just to finish off on a question on leverage. I know on Slide 19, you've mentioned that the company is on track to reach its long-term targets in 2025. I know you've mentioned in the past that MVP provides the most immediate path to achieving your targets. So given that you've exited the year at 4.4x and you're about, let's call it, 0.4x away from your target, is it all MVP? Or are there other items that we should be considering for your deleveraging?

D
D. James Harbilas
executive

Maurice, it's James here. We've always said that MVP is obviously the quickest way for us to get there. And when we've been asked to triangulate what the deleveraging would be associated with MVP, that 0.4 to 0.5x was always a number that we cited as us being able to crystallize once that process is complete, and it would get us to that target.

M
Maurice Choy
analyst

And is it fair to say that whilst negotiations are ongoing, that 0.4x, 0.5x deleveraging remains true based on your outlook?

D
D. James Harbilas
executive

So in terms of the process, I can definitely comment on where we are in the process, but I'm not going to speculate further other than the data points that I've shared with you in terms of where that's going to land. But I can tell you that it's a very robust process. We're in the middle innings. Obviously, the parties that are interested in the assets are the global players that would be attracted to assets that have these kind of characteristics in the form of strong cash flows, strong growth embedded within the opportunities on the mainline and the Southgate expansion and obviously, strong counterparty credits.

So our time line continues to be the first half of 2025. That's what we embedded in our guidance from an MVP contribution standpoint. So we will be in a position when we release Q1 to provide further update on that process. But we see strong interest in this pipeline.

Operator

Next question will be from Robert Catellier at CIBC Capital Markets.

R
Robert Catellier
analyst

I was -- before the call, I was going to ask about REEF and now you met your tolling targets, what's your vision for further developing the site. You touched on methanol and some other opportunities. Can you give us maybe a broad outline of what you see as the pathway to the next potential FID either at RIPET or REEF. And on REEF and the methanol opportunity, do you see the customer set, the demand side customers as being -- having some overlap with your existing customers?

D
Dai-Chung Yu
executive

Rob, I think the methanol project is very exciting because that opens up the entire Asian market to us. Right now with the slightly higher methanol content that Canadian propane has, there is a slightly limited buyer set, which is predominantly in Korea and Japan, whereas if the methanol spec does come down a little bit, for sure, we'll be able to access the full Asian market, including PDH facilities in China. So the project itself is a modest amount of capital, but it fully opens up that 3 million-barrel a day Asian market, so that diversifies our customer mix. And I think we're -- it's fair to say we're working -- continuing to looking at tolling deals with Asian off takers, who really want to have that lower methanol spec.

So the commercial interest on REEF has obviously been very strong. And I think that's why in our prepared remarks, James talked about us kicking off engineering design and permitting work for REEF -- subsequent phase of REEF. Right now, we're just working through what the permitting process is going to look like as I think we were a little surprised by the strong customer -- the very strong customer demand we're seeing. So I think at our next Q1 call, we'll be able to give people more color on what that permitting time line could look like.

R
Robert Catellier
analyst

Okay. That's helpful. So there could be customer overlap, but really you have opportunity to broaden your market reach.

D
Dai-Chung Yu
executive

Yes. Materially broaden.

R
Robert Catellier
analyst

Yes. Okay. Just on the utilities. I know you spent some time over last number of months plus on some advocacy work with the regulator, et cetera. I'm wondering what progress you feel you've made towards getting some sort of weather protection specifically for the D.C. franchise?

D
Dai-Chung Yu
executive

So we have -- in our rate filing, we've requested weather normalization. Maybe I'll just turn it over to Blue and give you some color on the mechanics of what we've got in our rate case ask.

D
Donald Jenkins
executive

Yes. Thanks, Vern. So as Vern pointed out, we -- in our previous rate case, we did ask for weather normalization. We didn't get that, but we did get a conversation coming out of that rate case that the commission gave us a path to follow to try to bring that forward, which we have done.

That included working with our interveners, making sure that they understood what the benefits were to customers and how the process would work. We did file that subsequent weather normalization in the current rate case and the conversations to date, I'll say they're trending positive. I think the cold weather in Q1 helps that conversation in order to let customers plan accordingly for something that looks more like levelized bills based on average weather. So it's always tough to see where that will go, but the conversations with the commission and interveners through the process of both the last rate case and this one has trended positive in my view.

Operator

[Operator Instructions] Next will be Ben Pham at BMO.

B
Benjamin Pham
analyst

Question on your balance sheet capacity, capital allocation, the $1.4 billion CapEx this year. Is there room to add more to that before you hit credit rating scrutiny or having to need to tap equity markets?

D
Dai-Chung Yu
executive

Well, I think we're in the position, Ben, of spending $1.4 billion per year at our target credit metrics. And obviously, we have a little bit of work to do in 2025 to get to those target credit metrics. Our investment capacity will rise with Pipestone II, with REEF and subsequent rate cases at the utilities. So it's fair to say we're -- we've allocated capital to the best risk-adjusted project -- rewarding projects for '25 and then we're going to have to wait for a little bit more cash flow growth before we're able to allocate more capital to the business.

B
Benjamin Pham
analyst

And as you think about those '25 CapEx, even through [indiscernible], what's the thought process between midstream utility? Is it similar to this year, you think, where rate base growth is below 8%, you push more to midstream? Or do you see a scenario where that rate base growth can [ glide back ] to 8% or more?

D
Dai-Chung Yu
executive

Well, it's early days to start speculating about future projects. But I think the good news is we have lots of growth opportunities in front of us. The utility has 8% rate base growth coming from modernization, customer adds, and that could theoretically grow if we're successful with a number of these data center opportunities in Northern Virginia. In Michigan in front of us, we have -- I'm going to butcher this, the Keweenaw Connector, which is a highly -- very low risk modernization program for relatively large size for SEMCO and that's going through its regulatory process now.

So there's tons of opportunity in the utility. And then similarly, there's tons of opportunity in midstream where we've talked about REEF expansion -- further REEF expansions, Pipestone expansion, another Pipestone plant, North Pine expansion. So it's great to be in a position where we have a very significant competition for the investment capacity we have.

And as we continue to work to maximize the value of our existing assets, every time we increase $1 of cash flow, we increased our investment capacity. So that's why -- if you look at our strategic priorities, we're still focused on continuing to narrow that ROE gap at the utility and continuing to try to increase the utilization of our existing assets in midstream.

B
Benjamin Pham
analyst

Okay. And maybe just one last cleanup on MVP. I just wanted to check, is that your guidance, I assume that -- assuming the -- is the cash coming in post-FERC approval? And is it just FERC that you would need blessing on?

D
D. James Harbilas
executive

Sorry, can you just repeat that last part of the question in terms of approvals?

B
Benjamin Pham
analyst

Yes. Is it just -- I mean, after you announced a potential sale beyond that, what's the key milestone? Is it just a FERC side approvals? And then your guidance, I just wanted to check when you say midyear or whatnot, I'm assuming that's when you get the cash coming in post approval.

D
D. James Harbilas
executive

That's right. Yes. I mean, obviously, the way we've incorporated MVP contributions into our guidance was for 6 months of EBITDA and equity pickup from that asset. So we do feel that we can complete our process inclusive of approvals in that first 6 months, the way we've laid out the time lines for round 2. And if you look as a benchmark to the EQT [ Blackstone ] transaction that included some other FERC-regulated assets, we anticipate that those approvals would be very quick to receive.

Operator

This concludes the Q&A portion of today's call. I would like to turn the call back over to Mr. Swanson.

A
Aaron Swanson
executive

Thanks, Sylvie. Thank you, everyone, for joining the call once again. Have a great Friday.

Earnings Call Recording
Other Earnings Calls
Get AI-powered insights for any company or topic.
Open AI Assistant

Intrinsic Value is all-important and is the only logical way to evaluate the relative attractiveness of investments and businesses.

Warren Buffett